Daniel Sabatino |
Ongoing 2021 |
$2.7m |
6 Months |
PROJECT NAME : Scotch College Wellbeing & Sports Centre
LOCATION : Torrens Park, SA
D&V Services have been working on the Scotch College project since January 2021, performing civil site works to make way for the new Wellbeing and Sports Centre for the Torrens Park College.
The project consists of the complete site clearance, including locating services, removal of all landscape and vegetation, kerbs, and footpaths, as well as redundant stormwater.
Upon a cleared site, the new works consisted of bulk earthworks, base preparation, installation of retaining walls, detailed excavation for the new 25m swimming pool, preparation of subgrade, benching, supply and installation of asphalt, paving, bollards, and line marking as well as stormwater and irrigation.
During the excavation project asbestos fragments were discovered throughout the soil, our team quickly mobilised our asbestos technicians to site and are working closely with an Environmental Consultant to complete the segregation and removal of the contaminated fill from site for disposal.
View the embedded image gallery online at:
https://www.dvservices.com.au/projects/item/45-scotch-college-wellbeing-sports-centre.html#sigProId9f8f0ef61e
https://www.dvservices.com.au/projects/item/45-scotch-college-wellbeing-sports-centre.html#sigProId9f8f0ef61e